Water Treatment Plant Control Upgrade – Coromandel

Kinetic Electrical East Tamaki was commissioned by the Thames-Coromandel District Council to upgrade the main switch board and control panel as well as upgrade the existing PLC, all while maintaining town water supply to drinking water standards.  Kinetic Electrical completed all aspects of the project including switchboard installation, control change over, rewiring of devices, and PLC programming.

Duration – four  Months
Staff Number Involved – four
Challenges – maintaining town water supply during upgrade. Transferring control of plant gradually.
Undertaken By – Kinetic Electrical East Tamaki

 