Pan Pac Slab Press Two Upgrade

 

To build up a new PLC panel, control panel and remote I/O cabinet.  Install new cables while maintaining an operational press.

Commissioning plant ready for operation.

Duration – two weeks
Staff Number Involved – seven
Challenges – working on operational equipment and a change-over period of 60 hours, with an operational deadline
Undertaken By – Kinetic Electrical Hawke’s Bay

 